Applications must be for a brand-new project or extend previously or currently funded work to create substantively new products, applications or processes
Eligible costs must be incurred in the UK
Subsidy recipients must intend to exploit the results of the project activity in the UK
Projects should aim for a start date of 1 February 2027, where possible
All grant-funded activities must be completed by 30 January 2030
Projects must meet specified Technology Readiness Level and Commercial Readiness Level criteria
Projects whose innovations materially influence heat pump system energy performance must demonstrate that the innovation, as part of a complete heat pump system, can achieve a Seasonal Performance Factor of at least 3.5 in a real-world home environment by the end of the funded project period
This includes recording a minimum of 12 months of performance data on an in-situ innovative heat pump system trialled within a home.